Influence of Grouting Interruption on Mechanical Performance of Offshore Wind Turbine Jacket Foundation Connection

Authors

  • Xingzheng Zhou
  • Zhaoqi Wu
  • Siquan Jiang
  • Zhi Li
  • Dongya Zhang
  • Chengyuan Zhang

DOI:

https://doi.org/10.54097/zcrerd51

Keywords:

Offshore wind power, jacket foundation, grouting connection, grouting pipe plugging, carrying capacity, FEA

Abstract

Offshore working environment is complex and variable, and sometimes the grouting pipe is blocked and cannot be continued in the offshore wind power jacket foundation. In this paper, the effect of grouting interruption on the mechanical performance of jacket foundation connection was analyzed by numerical simulation. Firstly, a finite element analysis model for the axial force behavior of grouting connection was established, and the validity was verified by existing experiments. Then three different simulation methods of grouting interruption were compared and analyzed. Moreover, the parameters of grouting break position, shear key height, shear key spacing, the thickness of grouting body and the number of shear key were analyzed. Based on the analysis results, a calculation method of bearing capacity for rapid assessment of the grouting interruption was established.

Downloads

Download data is not yet available.

References

[1] Liu Jizhen, Ma Lifei, Wang Qinghua, Fang Fang, Zhu Yankai. Offshore Wind Power Supports China’s Energy Transition [J]. Strategic Study of CAE, 2021, 23(1): 149-159.

[2] Wang wei, Yang Min. Design theory and engineering application for foundation of offshore wind turbine [M]. Beijing: China Building Industry Press, 2014.

[3] DNVGL-ST-0126, Support Structures for Wind Turbines [S], 2021.

[4] Lee J H, Won D H, Jeong Y J, et al. Interfacial shear behavior of a high-strength pile to sleeve grouted connection [J]. Engineering Structures, 2017, 151:704-723.

[5] Wang GenLiang. Research on axial mechanical properties of large-diameter high-strength grouted joints [D]. Fuzhou: Fuzhou University, 2020.

[6] Aritenang W, Elnashai A S, Dowling P J, et al. Failure mechanisms of weld-beaded grouted pile/sleeve connections [J]. Marine Structures, 1990, 3(5):391-417.

[7] Chen Zehao. Analysis of axial force performance of new grouted joint section of offshore wind power foundation [D]. Fuzhou: Fuzhou University, 2018.

Downloads

Published

10-01-2025

How to Cite

Zhou, X., Wu, Z., Jiang, S., Li, Z., Zhang, D., & Zhang, C. (2025). Influence of Grouting Interruption on Mechanical Performance of Offshore Wind Turbine Jacket Foundation Connection. Highlights in Science, Engineering and Technology, 126, 44-52. https://doi.org/10.54097/zcrerd51